110th Avenue Opens, Work Starts on Montebello
This is a Road Construction Update from the City of Wilsonville Engineering Department
Construction Cones 110th
The "Local Traffic Only" restriction has been lifted from 110th Avenue. The road will continue to be open until Spring 2008, when a final paving layer will be applied. For more information on this project, please see the Boeckman Road Extension section of the Street Projects page.
Montebello
Waterline replacement is underway on Montebello, starting from Evergreen Avenue and moving south to Wilsonville Road. Work is scheduled to be complete by January 25th. Motorists may experience up to 20 minute delays as traffic control flaggers direct one-lane traffic around the work zone. Non-local traffic is encouraged to bypass this road if possible.
We appreciate your patience with our improvements! For comments or questions, please use our online Citizen Requests form or contact Engineering at 503-682-4960.